DOWN TOWN INFRASTRUCTURE
FORT MORGAN, CO
$3.1 million

The Fort Morgan project comprised of the demolition of 2 blocks in Downtown Fort Morgan, and installation of storm pipe (5,847 LF), water main (2,600LF), water services and extensive 3-color concrete flatwork and permeable paving parking areas. Including installation of concrete seatwalls, new traffic signals, and 1/2 mile of new asphalt roadway on Main Street. All businesses remained open during construction and the project was substantially completed within the contractual 90 day schedule.

Other features include:

  • Extensive Road and Utility Demolition
  • New Asphalt Roadway
  • Replacement of existing signals and site lighting
  • 17,000 SF of Permeable Pavers
  • New Decorative Concrete Sidewalks
  • New Entry Sign and Seatwalls

PROJECT SPECIFICATIONS

Opening Year: 2009

Project Partners:
City of Fort Morgan  
Engineer: SEH

Schedule:
Start 06/09
Completion 09/09

Project Responsibilities:
Coordination of trades
Budget Management
Schedule Conformance