FORT MORGAN, CO
$3.1 million
The Fort Morgan project comprised of the demolition of 2 blocks in Downtown Fort Morgan, and installation of storm pipe (5,847 LF), water main (2,600LF), water services and extensive 3-color concrete flatwork and permeable paving parking areas. Including installation of concrete seatwalls, new traffic signals, and 1/2 mile of new asphalt roadway on Main Street. All businesses remained open during construction and the project was substantially completed within the contractual 90 day schedule.
Other features include:
- Extensive Road and Utility Demolition
- New Asphalt Roadway
- Replacement of existing signals and site lighting
- 17,000 SF of Permeable Pavers
- New Decorative Concrete Sidewalks
- New Entry Sign and Seatwalls