NORTHGLENN, CO
$3.4 million
This extensive site project entails demolition of existing infrastructure and reconstruction of Huron St., including new lake overflow structure. Croke Reservoir shore stabilization was a beautification project which entailed a clean up of the surrounding streetscape as well as a one mile soft surface trail and decorative plaza with water features.
Other features include:
- Overflow structure and piping of 60’’ and 48’’ storm sewer across Huron Ave.
- Waterline replacement
- Dewatering and excavation
- Extensive rip-rap work and grading of Croke Reservoir
- Retaining wall construction
- Traffic control and traffic signal work
- Roadway signage and striping