This fast-track, Phase I project in the center of a busy Colorado State University campus required up-front value engineering from ECI. The result: ECI provided cost-effective alternatives and was able to meet the project budget. Construction over just three months included:
extensive concrete flatwork
concrete retaining walls with flagstone veneer
masonry entry sign
security gates
bus benches
custom fabricated bus shelters
information kiosk
asphalt paving
landscaping
custom signage
site electrical
PROJECT SPECIFICATIONS
Opening Year: 2002
Project Partners: City of Fort Collins
Architect: Coover-Clark &
Associates, P.C.
Schedule: Start 05/02
Completion 08/02
Project Responsibilities: Coordination of trades
Budget Management
Schedule Conformance