ECI worked closely with the City of Boulder throughout this project, especially when the City needed to redesign plans to avoid intruding on sensitive wildlife habitats. To keep the project moving smoothly during the unexpected redesign, ECI held the project open during the winter of 2001-02 to give the city time to complete the project using the updated designs. Specific ECI work for this community park included:
earthwork
intensive site drainage
utility installation
concrete trails
signage
asphalt parking lot
site amenities
site electrical
pedestrian foot bridges
feature boulders and rock walls
pavers
landscaping, seed, sod and irrigation
PROJECT SPECIFICATIONS
Opening Year: 2002
Project Partners: City of Boulder
Architect: McLaughlin
Water Engineers, Inc
Schedule: Start 03/01
Completion 04/02
Project Responsibilities: General Contractor
Coordination of trades
Budget Management
Schedule Conformance