PROJECT SPECIFICATIONS

General Contractor:
ECI Site Construction Management
P.O. Box 2135
Loveland, CO 80539

Project Manager:
*Ted Johnson
Superintendent:
*Rick Coulter

Contract Amount:
$2,237,583.00

Construction Schedule: 03/01-04/02

Contacts:
City of Boulder
3198 North Broadway
Boulder, CO 80304
   Maureen Spitzer
   Owner's Representative
    (303) 413-7226

McLaughlin Water Engineers, Inc
Now-ASCG
2420 Alcott Street
Denver, CO 80211
    Brian Chevalier
    Engineer/Project Manager
    (303) 458-5550

Project Responsibilities:
General Contractor
Channel Construction
Demolition
Trail Construction
Traffic Control
New Box Headwall Construction

ECI Site Construction Management
VALMONT PARK & WONDERLAND CHANNEL
BOULDER, CO

ECI worked closely with the City of Boulder throughout this project when the City needed to redesign plans to avoid intruding on sensitive wildlife habitats. To keep the project moving smoothly during the unexpected redesign, ECI held the project open the winter of 2001-2002. This gave the City time to complete the updated designs in order for ECI to finish the project. Specific work on this community park included:

  • Earthwork and utility installation
  • Intensive site drainage
  • Concrete trails and asphalt parking lot
  • All site electrical, signage, and site amenities
  • Pedestrian foot bridges, feature boulders, and rock walls
  • Pavers with landscaping, sod, seed, and irrigation

Valmont / Wonderland Channel
Valmont / Wonderland Channel
Valmont / Wonderland Channel
Click images to enlarge.

 

 